119-03 LINDEN BOULEVARD

119-03 LINDEN BOULEVARD

Developer

NineDot Energy

Status

Pre-Construction

Borough

Queens

Capacity

4.9

Metering

S-SFA

Start

Start

Interconnection Application Date
Interconnection Application Date
December 2021
December 2021
Queue
Upgrade Cost Full Payment
Upgrade Cost Full Payment
June 2023
June 2023
$718,254.42

Last Movement: Apr 2025

Start

Development Timeline

Development Timeline

Development

Planning Start

Nov 2023

Development Planning Start

Development Start

Nov 2024

Active Development Start