121 VETERANS ROAD WEST

121 VETERANS ROAD WEST

121 VETERANS ROAD WEST

Developer

NineDot Energy

Status

Pre-Construction

Borough

Staten Island

Capacity

4.95

Metering

RC

Start

Start

Start

Interconnection Application Date
Interconnection Application Date
Interconnection Application Date
June 2020
June 2020
June 2020
Queue
Upgrade Cost Full Payment
Upgrade Cost Full Payment
Upgrade Cost Full Payment
April 2021
April 2021
April 2021
$537,931.49

Last Movement: Jun 2025

Start

Start

Development Timeline
Development Timeline
Development Timeline
Development

Planning Start

Nov 2022

Development Planning Start

Development Start

May 2023

Active Development Start

Project Financials