15 TILLMAN STREET

15 TILLMAN STREET

Developer

NineDot Energy

Status

Pre-Construction

Borough

Staten Island

Capacity

3

Metering

S-SFA

Start

Start

Interconnection Application Date
Interconnection Application Date
November 2021
November 2021
Queue
Upgrade Cost Full Payment
Upgrade Cost Full Payment
July 2023
July 2023
$4,107,153.25

Last Movement: Feb 2025

Start

Development Timeline

Development Timeline

Development

Planning Start

Dec 2023

Development Planning Start

Development Start

Jan 2025

Active Development Start