2380 ARTHUR KILL ROAD

2380 ARTHUR KILL ROAD

2380 ARTHUR KILL ROAD

Developer

NineDot Energy

Status

Operational

Borough

Staten Island

Capacity

4.95

Metering

RC

Start

Start

Start

Interconnection Application Date
Interconnection Application Date
Interconnection Application Date
June 2020
June 2020
June 2020
Queue
Upgrade Cost Full Payment
Upgrade Cost Full Payment
Upgrade Cost Full Payment
April 2021
April 2021
April 2021
$375,361.53

Last Movement: May 2025

Start

Start

Development Timeline
Development Timeline
Development Timeline
Development

Planning Start

Aug 2022

Development Planning Start

Development Start

Sep 2022

Active Development Start

Operational

Dec 30, 2024

Interconnection Queue

Final Letter of Acceptance

Project Financials