NELSON AVENUE

NELSON AVENUE

NELSON AVENUE

Developer

NineDot Energy

Status

Pre-Construction

Borough

Staten Island

Capacity

4.95

Metering

CDG

Start

Start

Start

Interconnection Application Date
Interconnection Application Date
Interconnection Application Date
March 2021
March 2021
March 2021
Queue
Upgrade Cost Full Payment
Upgrade Cost Full Payment
Upgrade Cost Full Payment
December 2021
December 2021
December 2021
$1,469,914.74

Last Movement: Mar 2025

Start

Start

Development Timeline
Development Timeline
Development Timeline
Development

Planning Start

Nov 2022

Development Planning Start

Development Start

Nov 2023

Active Development Start

Project Financials