RUST STREET

RUST STREET

RUST STREET

Developer

Microgrid Networks

Status

Operational

Borough

Queens

Capacity

5

Metering

CDG

Start

Start

Start

Interconnection Application Date
Interconnection Application Date
Interconnection Application Date
September 2021
September 2021
September 2021
Queue
Upgrade Cost Full Payment
Upgrade Cost Full Payment
Upgrade Cost Full Payment
April 2022
April 2022
April 2022
$324,678.77

Last Movement: Dec 2023

Start

Start

Development Timeline
Development Timeline
Development Timeline
Development

Planning Start

Sep 2021

Development Planning Start

Development Start

Jul 2022

Active Development Start

Operational

Nov 10, 2023

Interconnection Queue

Final Letter of Acceptance

Project Financials