SNEDEN AVENUE

SNEDEN AVENUE

SNEDEN AVENUE

Developer

NineDot Energy

Status

Operational

Borough

Staten Island

Capacity

4.95

Metering

RC

Start

Start

Start

Interconnection Application Date
Interconnection Application Date
Interconnection Application Date
February 2021
February 2021
February 2021
Queue
Upgrade Cost Full Payment
Upgrade Cost Full Payment
Upgrade Cost Full Payment
December 2021
December 2021
December 2021
$899,692.8

Last Movement: Sep 2022

Start

Start

Development Timeline
Development Timeline
Development Timeline
Development

Planning Start

Sep 2019

Development Planning Start

Development Start

Feb 2020

Active Development Start

In Review

June 2023

Date Development Signed Off

Final Site Sign-Offs

Operational

Dec 16, 2024

Interconnection Queue

Final Letter of Acceptance

Project Financials